NAFTA - Chapter 11 - Investment

Mercer International Inc. v. Government of Canada

Before the additional facility of the international centre for settlement of investment dispute (ICSID)

Between:

Mercer International Inc.
Claimant / Investor

And:

Government of Canada
Respondent / Party

ICSID case no. ARB(AF)/12/(3)


Government of Canada
Rejoinder Memorial

31 March 2015


Sections and excerpts identified as "[REDACTED]" represent redactions in the official version of this document.

Please see full Canada's Rejoinder Memorial Public Version (PDF 2.77 MB)


Departments of Justice and of
Foreign Affairs, Trade and Development
Trade Law Bureau
Lester B. Pearson Building
125 Sussex Drive
Ottawa, Ontario
K1A 0G2
Canada

Executive Summary

1. Proponents responding to a competitive call for the procurement of energy sometimes disagree with the contractual terms and conditions proposed, which define the parameters of the procurement. In these circumstances, the proponent has a choice: it can accept these terms and conditions; it can attempt to negotiate new terms and conditions; or it can walk away from the process. It is not reasonable, however, for a proponent to expect the procuring entity to offer terms and conditions that differ fundamentally from the mandate of the call and that would effectively reduce the amount of the energy procured.

2. This is precisely what the Claimant alleges should have happened when it claims that BC Hydro should not have “imposed” a “restriction” on Celgar through the exclusivity clause in its Electricity Purchase Agreement (“EPA”). It also complains that the B.C. Utilities Commission (“BCUC”) effectively continued this “restriction” on its ability to sell electricity in Order G-48-09. Much of the Claimant’s case now appears to rest on these supposed “restrictions.” The Claimant, however, also continues to complain about the amount of electricity BC Hydro procured when it set a Generator Baseline (“GBL”) for Celgar.

3. The Claimant in complaining about these “restrictions” expects this Tribunal to assume the role of BC Hydro, a state enterprise, in the context of a competitive procurement so that it can assess the commercial reasonableness of the exclusivity clause, which applied to all proponents. It also requests this Tribunal to substitute its judgement for that of BC Hydro when it made complex and highly technical decisions concerning the amount of electricity it would procure when it set GBLs. The Tribunal is then expected to vault into the role of the BCUC to interpret its previous regulatory decisions and replace the BCUC’s weighing and balancing of what is in the “public interest” with decisions that would only be in the Claimant’s interest. It is not the role of a NAFTA Chapter 11 tribunal to act in the stead of state enterprises and administrative tribunals in this manner.

4. Perhaps more importantly, the Claimant’s alleged “restrictions” are not really restrictions at all. The Claimant asserts that BC Hydro used the exclusivity clause to “force”Footnote 1 Celgar to use its self-generated electricity for its own load and to prevent it from selling its electricity in the U.S. market. Mr. Merwin tries to paint BC Hydro in an unfavourable light alleging that it foisted the clause on Celgar in the context of the EPA negotiations at the “11th hour,” leaving the Claimant with no choice but to accept it.Footnote 2

5. Nothing could be further from the truth. The exclusivity clause is a standard provision of every EPA (including the Tembec and Howe Sound EPAs) and formed part of the terms and conditions when the Claimant made its bid into the competitive call for power. As Mr. Scouras explains in his second witness statement, it was Mr. Merwin who requested the removal of the clause relatively late in the negotiations.Footnote 3

6. The exclusivity clause ensures that BC Hydro will have security of supply under the EPA, and thus its removal was a concern. BC Hydro nonetheless “wanted to be responsive to the interests of Celgar”Footnote 4 and proposed a compromise—a Side Letter Agreement that would require the parties to amend the exclusivity clause if the BCUC decided that Celgar could sell below-GBL electricity in “any pending or future regulatory proceeding.Footnote 5 No other pulp mill in British Columbia has received an accommodation similar to the Side Letter Agreement.Footnote 6

7. Mr. Merwin’s testimony leaves the impression that BC Hydro strong-armed Celgar into accepting the exclusivity clause in the EPA.Footnote 7 This misleading version of events, however, is contradicted by Mr. Merwin’s own contemporaneous report to his CEO on this issue, which indicates that:

  • [O]n Friday Hydro added one major wrinkle to our negotiations. This wrinkle was not unexpected and approximately 4 weeks ago we had reached agreement on how this issue would be addressed. The issue at hand is our current activities to allow us to sell all of Celgar’s existing generation (the Arbitrage Project). …A number of weeks ago we reached agreement with Hydro that we would leave this issue for the BC Utilities Commission to decide and withdrew the term from the EPA and agreed to set up a side letter acknowledging this withdrawal and that neither party could use this omission to further their argument. BC Hydro came back to us on Friday with the position the wording should be left in the contract to prevent us from selling our mill load and we would have a side letter acknowledging that subject to certain conditions this term would be removed. … They however indicated they are prepared to live by the principles we established several weeks ago which [sic] was to leave this to the BCUC to decide.Footnote 8

8. This email stands in stark contrast to how the Claimant and Mr. Merwin now attempt to characterize the discussions concerning the exclusivity clause in the context of the EPA negotiations.Footnote 9

9. BC Hydro and the Claimant subsequently negotiated the Side Letter Agreement and executed it alongside the EPA on January 27, 2009.Footnote 10 The parties effectively agreed in the Side Letter Agreement that they would to leave it to the BCUC to decide the issue of Celgar’s sales of below-load electricity.

10. BC Hydro had separately applied to the BCUC to determine whether FortisBC was permitted under the terms of its 1993 Power Purchase Agreement (“1993 PPA”) with BC Hydro to supply electricity to customers such as the City of Nelson and Celgar who intended to engage in arbitrage. The Claimant intervened in this proceeding to push its buy all, sell all scheme. Mr. Merwin, contrary to his most recent testimony,Footnote 11 was fully aware that there was a risk that the BCUC could reject his “Arbitrage Project.” Mr. Debienne, Vice President of Power Supply and Strategic Planning for FortisBC, had discussed with Mr. Merwin the relevant BCUC regulatory precedents and informed him that there was a 50 percent chance that the BCUC could reject the project.Footnote 12 The Claimant had also advised its Board of Directors of this regulatory risk.Footnote 13

11. FortisBC’s reservations turned out to be right. The BCUC in Order G-48-09 amended the 1993 PPA to prevent FortisBC from selling electricity supplied under this agreement to a customer that was selling electricity below their load (i.e., engaging in arbitrage). The Claimant characterizes Order G-48-09 as the second “restriction” on its ability to sell below-GBL electricity because it allegedly “prevents” FortisBC from supplying any embedded cost energy to facilitate arbitrage. This, however, mischaracterises Order G-48-09, which places no restrictions on FortisBC’s ability to source the Claimant from its own embedded cost resources.

12. The Claimant, for this reason, would subsequently request the BCUC to direct FortisBC to develop a matching methodology which would allow FortisBC to supply Celgar using non-1993 PPA sources of electricity. The Claimant argued that that this non-PPA electricity could then be “matched” against its load so that it could engage in below-load sales without arbitraging electricity under the 1993 PPA.Footnote 14 FortisBC agreed that this approach might be feasibleFootnote 15 and the BCUC thus directed FortisBC in Order G- 188-11 to develop a rate based on this “matching methodology.” The BCUC also confirmed that “Celgar is free to sell all or a portion of its generation below the BC Hydro GBL into the market and supply its mill from FortisBC resources, not including BC Hydro PPA Power.”Footnote 16 Indeed, Mr. Merwin would explain to his Board of Directors that BCUC Order G-188-11 was a “major victory”.Footnote 17

13. Mr. Merwin would also write BC Hydro shortly after BCUC Order G-188-11 to request that it exercise the Side Letter Agreement and amend the exclusivity clause from the EPA.Footnote 18 BC Hydro was not adverse to this request and contacted FortisBC to discuss how the accounting would be done for Celgar’s EPA sales to BC Hydro in conjunction with the new rate.Footnote 19 Regrettably, the Claimant then decided instead that it would file its Notice of Intent under the NAFTA and never followed-up with its request.Footnote 20

14. FortisBC subsequently proposed a “Non-PPA Embedded Cost Power” (“NECP”) rate to facilitate the Claimant’s below-GBL sales.Footnote 21 The BCUC in Order G-202-12 confirmed that the Claimant could nominate as much as 100% percent of its loadFootnote 22 for service from FortisBC using the NECP rate.

15. The Claimant argues in this arbitration that the NECP rate would not reflect “traditional” embedded cost rates and that “[u]nlike all other FortisBC customers, Celgar would receive none of the benefit of FortisBC’s existing, low cost generation assets.”Footnote 23 This is not accurate. Mr. Dennis Swanson, Vice President of Corporate Services for FortisBC, explains that the NECP rate would be sourced from all of FortisBC’s resources with the exception of BC Hydro’s 1993 PPA electricity.Footnote 24 These resources would include FortisBC’s traditional embedded cost power from sources such as its hydro-electric facilities. He also explains that the NECP rate would have been no higher than the rates Celgar has received since BCUC Order G-48-09.Footnote 25

16. The Claimant’s argument that the BCUC has imposed a “restriction” that has denied it “access” to embedded cost power is thus false.Footnote 26 The BCUC has in fact made considerable efforts to accommodate the Claimant’s demands to sell its below-GBL electricity. The Claimant has criticized the NECP rate even though it suggested this approach as a solution.Footnote 27 In any event, the fact that a customer of one utility could have a slightly higher rate than a customer of anther utility is not a valid ground for a NAFTA complaint—especially when the customer has requested this rate so that it can secure a right to sell electricity in a way that no other self-generating customer has in the province.

17. The Claimant’s intransigence over the NECP rate is also surprising in light of its repeated assertions that it could sell its electricity as “green” or renewable energy at prices that would surpass the cost of the NECP. For example, Mr. Merwin testifies that he “targeted [REDACTED] as a prospective buyer” and had “fruitful preliminary discussions.”Footnote 28 Roger Garrett of Puget Sound, however, testifies that he has no recollection of the ClaimantFootnote 29 and that Claimant’s electricity would not have, in any event, qualified as renewable or green energy under Washington state law.Footnote 30

18. Canada raised significant concerns in its Counter-Memorial over the Claimant’s failure to provide evidence that it could sell its electricity to third parties.Footnote 31 In its Reply, the Claimant again failed to provide any meaningful evidence and merely recycled the same unsupported claims that it made in its Memorial. Canada thus contacted Michael McDougall, Director of Trade Policy and Information Technology of Powerex, and Dean Krauss, Director of Business Development and Contract Services for NorthPoint, the Claimant’s former electricity broker, to determine whether the Claimant could actually have sold its electricity in the manner that Mr. Merwin and its experts suggest.

19. Mr. McDougall testifies that Celgar’s electricity was not eligible as renewable electricity in the states of Washington,Footnote 32 Oregon,Footnote 33 Montana,Footnote 34 California,Footnote 35 New Mexico,Footnote 36 and Arizona.Footnote 37 He also explains that Alberta, Idaho, Wyoming and Utah do not have renewable energy markets.Footnote 38 Mr. Krauss also explains that NorthPoint has never sold “green” or renewable electricity.Footnote 39 The Claimant thus had no market for this electricity as renewable energy. Nor did it have a broker that had experience marketing renewable energy.

20. Mr. McDougall and Mr. Krauss also explain that U.S. wholesale electricity prices tumbled towards the end of 2008, a few months after the peak prices the Claimant repeatedly refers to in its pleadings,Footnote 40 and that these electricity prices have remained low since that time at first as a result of the U.S. recession and later due to the increase in U.S. shale gas production.Footnote 41 Mr. McDougall and Mr. Swanson have also provided NERA’s Dr. Rosenzweig with data concerning Mid-Columbia market prices, line losses and transmission costs. Dr. Rosenzweig has “done the math” with this data and concluded that the Claimant could not have sold its electricity in a profitable manner on the Mid-Columbia market in the manner described in their Reply from 2009 onwards.Footnote 42 Mr. McDougall and Mr. Krauss also explain some of the numerous transmission challenges the Claimant would face marketing its electricity in the United States.

21. For this reason, the Claimant is forced in its Reply to claim that BC Hydro would procure all of the Claimant’s below-load electricity absent the measures while in the same breath stating that BC Hydro is “not legally obligated to buy it.”Footnote 43 The Claimant’s argument remains nothing more than a thinly veiled attempt to realize the profits from its “Arbitrage Project”, which BC Hydro properly rejected in the context of the Bioenergy Call for Power.

22. The Claimant spends hundreds of pages alleging that BC Hydro had no GBL methodology,Footnote 44 that it set the Claimant’s GBL with “no rules”,Footnote 45 that it has fabricated a “current normal” GBL methodology,Footnote 46 that even if such a standard existed it was applied less favourably to the Claimant,Footnote 47 and that in any event the energy policies underlying BC Hydro’s procurement of electricity are “not legitimate.”Footnote 48 Each one of these baseless accusations has been made to support a claim that BC Hydro set the Claimant’s GBL “too high,”Footnote 49 and that the Claimant should be compensated on the basis of a “nondiscriminatory GBL.” This is most evident in Table 12 of Mr. Kaczmarek’s most recent report which provides the Tribunal with numerous GBL “options,” all of which are lower than the Claimant’s actual GBL of 40 MW. Mr. Kaczmarek then proceeds to quantifies damages on the basis that the proper “but-for” world is one where BC Hydro should have procured additional electricity.Footnote 50 The Claimant seemly wants to transform this Tribunal into a “Court of GBLs” asking it to examine these GBLs in granular detail, frequently without any evidence that another pulp mill in like circumstances received the same treatment.

23. The Claimant and its experts continue to allege that BC Hydro afforded the Howe Sound and Skookumchuck pulp mills more favourable treatment when it set their GBLs. It does so with little regard for the unique technical and operational circumstances of each mill. Canada has already submitted witness statements from Pierre Lamarche and Fred Fominoff concerning these critical differences at the Howe Sound pulp mill.Footnote 51 Mr. Christian Lague, the Energy Manager at the Skookumchuck pulp mill, has now submitted a witness statement with this Rejoinder that confirms the basis on which BC Hydro determined a GBL for the 2009 Tembec EPA.Footnote 52

24. The Claimant’s case also fails for an entirely different reason—it is required to use its 52 MW turbine to provide electricity to meet its mill load. This commitment was made during a proposed expansion of the pulp mill in the early 1990s where the Claimant’s predecessor, Celgar Pulp Co., repeatedly used energy self-sufficiency as a selling point for the project’s approval.

25. Mr. Ostergaard and now Dr. Jon O’Riordan, the former Assistant Deputy Ministers from the Ministries of Energy and Environment, were responsible for supervising the review of Celgar Pulp Co.’s Energy Project Certificate application and both testify that Celgar’s representation that it would use this electricity for the purpose of load displacement was a critical consideration in approving the application and issuing the Ministers’ Order.Footnote 53 Ms. Denise Mullen, the Director of the Projects and Policy Branch after Mr. Ostergaard, explains that the Ministry would have expected the Celgar Pulp Co. to request an amendment to the Ministers’ Order if it intended to use the electricity for a purpose other than load displacement. Rather than request an amendment, the Claimant has instead raised numerous arguments in an attempt to evade the obligations imposed by this order, or alternatively, to render it unenforceable.

26. Finally, Canada will explain the Claimant’s strategy of using BCUC litigation as a means to “[REDACTED]Footnote 54 by raising issues that would have “[REDACTED].”Footnote 55 The Claimant was able to adopt this strategy because applicants such as FortisBC normally underwrite much of the cost of intervenors in BCUC proceedings. This improper litigation strategy has contributed to an annual rate increase of 1.5% for all ratepayers in FortisBC’s service area.Footnote 56

27. Canada submits that Claimant’s allegations when properly understood are devoid of factual or legal merit. Canada therefore requests that the Tribunal dismiss these claims and award Canada its full costs in this arbitration.

Footnotes

Footnote 1

Claimant’s Reply, ¶ 1.

Return to footnote 1 referrer

Footnote 2

Brian Merwin Statement II, ¶ 13. (“Just before the presentation to its Board, however, BC Hydro insisted on changing the text of Section 7.4, in a new Version 8 of the draft EPA, to preclude Celgar from selling its below-GBL energy to a third party. I remember this change well, as I was on vacation with my family at the time, and this 11th hour highly significant change disrupted that vacation”.)

Return to footnote 2 referrer

Footnote 3

Jim Scouras Statement II, ¶ 18.

Return to footnote 3 referrer

Footnote 4

Jim Scouras Statement II, ¶ 25.

Return to footnote 4 referrer

Footnote 5

Jim Scouras Statement II, ¶ 25. [Emphasis added.]

Return to footnote 5 referrer

Footnote 6

Jim Scouras Statement II, ¶ 33.

Return to footnote 6 referrer

Footnote 7

Brian Merwin Statement II, ¶¶ 12-13.

Return to footnote 7 referrer

Footnote 8

Email from Brian Merwin to David Gandossi and Jimmy Lee, RE: Celgar EPA negotiations with BC Hydro, 8 November 2008, MER00071253, R-528. [Emphasis Added]

Return to footnote 8 referrer

Footnote 9

See Brian Merwin Statement I, ¶¶ 102-105; Brian Merwin II, ¶¶ 11-13.

Return to footnote 9 referrer

Footnote 10

Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, RE: Electricity Purchase Agreement, with Effective Date of January 27, 2009, 27 January 2009, bates 026183-026184, R-138.

Return to footnote 10 referrer

Footnote 11

Brian Merwin Statement II, fn 30.

Return to footnote 11 referrer

Footnote 12

Dennis Swanson Statement II, ¶¶ 5 and 9-10.

Return to footnote 12 referrer

Footnote 13

Mercer International Group, Celgar Electricity Opportunities, July 2007, at 9-10, R-278. [REDACTED]

Return to footnote 13 referrer

Footnote 14

Letter from KC Moller to Alanna Gillis, Re: Zellstoff Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”) – Project No. 369836, dated August 15, 2011, attaching “Final Submissions of Zellstoff Celgar Limited Partnership”, p. 30, ¶¶ 6-15, R-529.

Return to footnote 14 referrer

Footnote 15

Letter from Ludmilla Herbst to Alanna Gillis, Re: Zellstoff Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, dated August 22, 2011, attaching Submissions of FortisBC, ¶ 57, R-530.

Return to footnote 15 referrer

Footnote 16

BCUC, Decision G-188-11, p. 49, R-275.

Return to footnote 16 referrer

Footnote 17

[Emphasis in Original.] Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, at MER00191043, R-531.

Return to footnote 17 referrer

Footnote 18

Letter from Brian Merwin to BC Hydro, December 6, 2011, R-485.

Return to footnote 18 referrer

Footnote 19

Jim Scouras Statement II, ¶ 38.

Return to footnote 19 referrer

Footnote 20

Notice of Intent to Submit a Claim to Arbitration under Chapter Eleven and Articles 1503(2) and 1502(3)(A) of the North American Free Trade Agreement, Mercer International Inc., v Government of Canada, ¶ 20, “[U]ntil November 2011 [i.e., until Order G-188-11] Celgar was the only pulp mill with self-generation capacity in the Province of British Columbia that was restricted from accessing any electric power from its local electric utility company, while selling to the market any of its self-financed, self- generated electric power.” The Claimant’s new position - that it has been “forced” to self-supply - conflicts with its own earlier pleadings.

Return to footnote 20 referrer

Footnote 21

Dennis Swanson Statement II, ¶ 27.

Return to footnote 21 referrer

Footnote 22

BCUC, Order G-202-12 and Decision, in the Matter of FortisBC Inc., Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012,¶ 3 of the Order, p. 3 of Decision, R-265.

Return to footnote 22 referrer

Footnote 23

Claimant’s Reply, fn. 256.

Return to footnote 23 referrer

Footnote 24

Dennis Swanson Statement II, ¶ 28.

Return to footnote 24 referrer

Footnote 25

Dennis Swanson Statement II, ¶¶ 33-35.

Return to footnote 25 referrer

Footnote 26

Claimant’s Memorial, ¶ 369. (“Since Order G-48-09 issued in May 2009, Celgar has been unable to access embedded cost utility electricity below its 2007 load, and thus has been unable to sell any of its below-load electricity.”)

Return to footnote 26 referrer

Footnote 27

Claimant’s letter to BCUC, August 15, 2011, p. 21, R-529. (“FortisBC’s concerns regarding jeopardizing its access to [PPA power] may be addressed through ensuring that any additional Celgar load served by FortisBC following the establishment of a FortisBC GBL is notionally matched to and served from additional third party energy purchases.”)

Return to footnote 27 referrer

Footnote 28

Brian Merwin Statement I, ¶¶ 82 and 144; Claimant’s Memorial, ¶ 298; Claimant’s Reply, ¶ 566.

Return to footnote 28 referrer

Footnote 29

Roger Garratt Statement, ¶¶ 15-16.

Return to footnote 29 referrer

Footnote 30

Roger Garratt Statement, ¶ 18.

Return to footnote 30 referrer

Footnote 31

Canada’s Counter Memorial, ¶ 507.

Return to footnote 31 referrer

Footnote 32

Michael McDougall Statement I, ¶¶ 73-80.

Return to footnote 32 referrer

Footnote 33

Michael McDougall Statement, ¶ 81.

Return to footnote 33 referrer

Footnote 34

Michael McDougall Statement, ¶¶ 82-83.

Return to footnote 34 referrer

Footnote 35

Michael McDougall Statement, ¶¶ 84-89.

Return to footnote 35 referrer

Footnote 36

Michael McDougall Statement, ¶ 94.

Return to footnote 36 referrer

Footnote 37

Michael McDougall Statement, ¶ 91.

Return to footnote 37 referrer

Footnote 38

Michael McDougall Statement I, ¶¶ 96-97. Mr. McDougall also explains that while it might be theoretically possible to sell to renewable energy in Nevada and Colorado the incentives in those markets have incentives for other forms of domestically produced renewable energy. Moreover, the distance of these renewable energy markets from British Columbia would make these sales impracticable. See Michael McDougall Statement, ¶¶ 93 and 95.

Return to footnote 38 referrer

Footnote 39

Dean Krauss Statement, ¶ 31.

Return to footnote 39 referrer

Footnote 40

Claimant’s Memorial, ¶ 298, Brian Merwin Statement I, ¶ 83, Claimant’s Reply, ¶ 507, and Robert Friesen Statement, ¶ 8.

Return to footnote 40 referrer

Footnote 41

Michael McDougall Statement I, ¶¶ 59-62; and Dean Kraus Statement I, ¶¶ 16 and 24.

Return to footnote 41 referrer

Footnote 42

NERA Expert Report II, ¶¶ 144-154.

Return to footnote 42 referrer

Footnote 43

Claimant’s Reply, ¶ 36.

Return to footnote 43 referrer

Footnote 44

Claimant’s Reply, pp. 124-221.

Return to footnote 44 referrer

Footnote 45

Claimant’s Reply, ¶¶ 513-520.

Return to footnote 45 referrer

Footnote 46

Claimant’s Reply, ¶¶ 263 and 266.

Return to footnote 46 referrer

Footnote 47

Claimant’s Reply, ¶ 291.

Return to footnote 47 referrer

Footnote 48

Claimant’s Reply, ¶ 181.

Return to footnote 48 referrer

Footnote 49

Claimant’s Reply, ¶ 553 [Emphasis added]

Return to footnote 49 referrer

Footnote 50

Navigant Expert Report II, p. 62.

Return to footnote 50 referrer

Footnote 51

Pierre Lamarche Statement I, ¶¶ 28-34; Pierre Lamarche Statement II, ¶¶ 4-11; Fred Fominoff Statement I, ¶¶ 15-20.

Return to footnote 51 referrer

Footnote 52

Christian Lague Statement I, ¶¶ 42-52.

Return to footnote 52 referrer

Footnote 53

Peter Ostergaard Statement I, ¶ 17; Jon O’Riordan Statement I, ¶ 75.

Return to footnote 53 referrer

Footnote 54

Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, MER00191043 at MER00191044, R-531.

Return to footnote 54 referrer

Footnote 55

Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, MER00191043 at MER00191044, R-531.

Return to footnote 55 referrer

Footnote 56

Dennis Swanson Statement I, ¶ 152.

Return to footnote 56 referrer